Migration project for the Laško Brewery
After months of work on programming the new process control system, Montelektro’s experts completed the migration project for Heineken Laško Brewery.
Share this article
The project included PCS migration from the old Botec and Otas-based system to the newest version of the brewmaxx system.
It consisted 10 000 components, 360 sequences, seven Siemens PLCs, the new optical backbone ring with nine PCD switches, two IT cabinets, 13 workstations, and seven brewmaxx OP panels.
Although it was a very complex project, the whole production process of the new PCS continued with minimal downtime.